UNIT -510
Renovation project complete. New balcony/screen porch addition painted to match existing building exterior. Final Inspection conducted May 30,2007.
Enjoy your renovated/expanded home!
New balconie view from the upstairs bedroom.
10 May, 2007 Construction Update
- Screen installed
- Triming work finished
- Safet installed
- Screen porch doors installed
- Preparing for tile installation
- Second floor railings installation started
Electrical wire-in-conduit installed to provide power for wall outlet and ceiling fan/light with switch inside screen new porch.
Handrail detail approved by SP ARB, also has to comply with International Building Code 2003 with picket spacing no more than 4" on center.
3/8" rough sawn plywood on the ceiling and KLEER Wood grain trim inside new screen porch.
04 May, 2007 Construction Update
- Electrical installation done
03 May, 2007 Construction Update
-
Screen porch framing built
-
Second floor porch framing done
-
Triming work started
-
Second floor railing installation started
Rear elevation view before renovation work.
|